Contract No:
HK/2009/05 Wanchai Development Phase II and Central Wanchai Bypass Sampling, Field Measurement and Testing Work
(Stage 1) Monthly Environmental Monitoring
& Audit Report
- MAY
2010 -
|
CLIENTS: |
|
Civil Engineering and Development
Department and Highways Department |
Lam Geotechnics Limited 11/F Centre Point 181-185 Gloucester Road, Wanchai,
H.K. Telephone: (852) 2882-3939 Facsimile: (852) 2882-3331 E-mail: info@lamenviro.com Website: http://www.lamenviro.com |
|
|
|
|
|
CHECKED
by: |
|
                         Raymond Dai Environmental Team Leader |
|
DATE: |
|
8 June 2010 |
1.1    Scope of the Report
1.2    Structure of the Report
2.   Project Background
2.1    Background
2.2    Scope of the Project and Site
Description
2.3    Division of the Project
Responsibility
2.4    Project Organization and Contact
Personnel
3.   status of regulatory compliance
3.1    Status of Environmental Licensing
and Permitting under the Project
4.   Monitoring Requirements
4.1    Noise Monitoring
4.2    Air Monitoring
4.3    Water Quality Monitoring
5.   Monitoring Results
5.1    Noise Monitoring Results
5.2    Air Monitoring Results
5.3    Water Monitoring Results
5.4    Waste Monitoring Results
6.1    Noise Monitoring
6.2    Air Monitoring
6.3    Water Quality Monitoring
6.4    Review of the Reasons for and the
Implications of Non-compliance
6.5    Summary of action taken in the
event of and follow-up on non-compliance
7.   Cumulative Construction Impact due to the Concurrent Projects
9.   Complaints, Notification
of Summons and Prosecution
lIST OF
TABLES
Table 2.1     Schedule 2 Designated Projects under this Project
Table 2.2    Details of Individual Contracts under the Project
Table 2.3    Contact Details of Key Personnel
Table 3.3    Summary of submission status under FEP-01/356/2009 Condition
Table 3.5    Summary of submission status under FEP-02/356/2009 Condition
Table 3.7    Summary of submission status under FEP-03/356/2009 Condition
Table 4.1    Noise Monitoring Station
Table 4.2    Air Monitoring Station
Table 4.3     Marine Water Quality Stations for Water Quality Monitoring
Table 4.4    Marine Water Quality Monitoring Frequency and Parameters
Table 5.1     Noise Monitoring Stations for Contract no. HY/2009/11
Table 5.2     Noise Monitoring Station for Contract nos. HK/2009/01 and HK/2009/02
Table 5.3     Air Monitoring Stations for Contract no. HY/2009/11
Table 5.4     Air Monitoring Stations for Contract no. HK/2009/01
Table 5.5     Air Monitoring Station for Contract no. HK/2009/02
Table 5.6     Water Monitoring Stations for Contract no. HY/2009/11
Table 5.7     Water Monitoring Stations for Contract no.HK/2009/01
Table 5.8     Water Monitoring Stations for Contract no. HK/2009/02
Table 5.9    Details of Waste Disposal for Contract no. HY/2009/11
Table 5.10   Details of Waste Disposal for Contract no. HK/2009/01
Table 5.11   Details of Waste Disposal for Contract no. HK/2009/02
Table 8.1    Summary of Environmental Inspections for Contract no. HY/2009/11
Table 9.1    Cumulative Statistics on Complaints
Table 9.2    Cumulative Statistics on Successful Prosecutions
lIST OF FIGUREs
Figure
2.1     Project
Layout
Figure
2.2     Project
Organization Chart
Figure 4.1      Locations
of Environmental Monitoring Stations
lIST OF APPENDIces
Appendix 3.1   Environmental Mitigation Implementation
Schedule
Appendix 4.1   Action
and Limit Level
Appendix
4.2   Copies of Calibration
Certificates
Appendix
5.1   Monitoring Schedule for
Reporting Month and Coming month
Appendix 5.2   Noise Monitoring Results and Graphical
Presentations
Appendix
5.3   Water Quality Monitoring Results and
Graphical Presentations
Appendix 6.1   Event
Action Plans
Appendix 6.2   Summary for Notification of Exceedance       
Appendix
9.1   Complaint Log
Appendix 10.1  Construction
Programme of Individual Contracts
Construction Activities for the
Reported Period
 -
Sediment dredging;
 -
Breakwater demolition;
 -
Special site hoarding
construction;
 -
Casting Caisson Seawall
(in Mainland China); and
 -
Casting Seawall Block (in
Mainland China)
 -
Erection of interim
Engineer’s Principal Office at Works areas WA2;
 -
Pre-drilling works and
fabrication of staging for trial pile, derrick barge is carrying out
transportation of materials to the designated pile position;
 -
Hoarding erection along
the southern and eastern side;
 -
Marine ground
investigation;
 -
Installation of
geotechnical instrumentation is underway and inclinometers points of E1, E2,
E3, E4 and E8
 -
Fabrication of pipe pile
wall staging at the existing promenade piled deck;
 -
Inspection and structural
condition survey, field measurement for pumping stations P1, P3, P4 and P5;
 -
Fabrication of special
made flat top barge for dredging inside the HKCEC water channel;
 -
Silt screens installation
for HKCEC Phase 1, Government Buildings, China Resources, Great Eagle &
Harbour Centre, Telecom House, Shui On and HKAPA;
 -
Temporary silt curtain
installation at HKCEC Extension (Pumping Station P6);
 -
Fabrication of silt
screens for Sheung Wan & Kowloon South Pumping Station, and remaining HKCEC
Extension;
 -
Temporary works on the
existing promenade piled deck for installation of pipe pile wall P1;
 -
Existing RC. Parapet on
the north side of water channel near Expo Drive West Bridge was removed
partially; removal of rock amour on sloping seawall is in progress;
 -
Fabrication of mud barges
and crane barge for dredging within HKCEC water channel; and
 -
Wheel washing facility at
the north entrance to the water channel.
 -
Installation of Silt
Screen and Silt Curtain;
 -
Construction of Temporary
Seawall (Sheet Pile);
 -
Road Modification Works;
 -
Removal Existing Footing
at WSD Salt Water Pumping Station;
 -
Pre-drilling Works at WSD
Salt Water Pumping Station;
 -
Site Clearance; and
 -
Hoarding Erection
Noise Monitoring
Air Quality Monitoring
Water Quality Monitoring
Suspended Solid
Turbidity
Complaints, Notifications of
Summons and Successful Prosecutions
Site Inspections and Audit
Table
I     Summary of Environmental
Inspections for Contract no. HY/2009/11
Date |
Observations |
Action taken by Contractor |
Outcome |
|
100504_01 |
4-May-10 |
Contractor is reminded to clean the debris behind the silt screen at
Sai Wan Ho. |
Daily clearance and inspection of silt screen. |
Complete as observed on 18-May-10 |
100512_01 |
12-May-10 |
Floating refuse
at WSD15 need to be cleaned up. |
Daily clearance and inspection of silt screen. |
Complete as observed on 18-May-10 |
100518_01 |
18-May-10 |
Floating refuse
was observed at C9. |
Daily clearance and inspection of silt screen. |
Complete as observed on 25-May-10 |
100518_02 |
18-May-10 |
Floating foam
of silt screen was observed lower than sea level at WSD17. It is reminded to
well maintain the condition of silt screen immediately. |
Follow-up
action is needed for coming site audit |
Outstanding as observed on 25 May 2010 |
100518_03 |
18-May-10 |
It is reminded to fence-off the silt curtain properly around the dredging
and filling
works area. |
Keep maintaining the silt curtain in well condition. |
Complete as observed on 25-May-10 |
100518_04 |
18-May-10 |
It is reminded to maintain and repair the silt screen at C8
regularly. |
Follow-up
action is needed for coming site audit |
Outstanding as observed on 25 May 2010 |
100525_01 |
25-May-10 |
A gap was found at the right side (view from boat) of the silt screen
at Quarry Bay. |
Follow-up action is needed for coming site audit |
Outstanding as observed on 25 May 2010 |
Future Key Issues
Contract no. HY/2009/11- North Point Reclamation
 -
Sediment dredging;
 -
Breakwater demolition;
 -
Casting Caisson Seawall
(in Mainland China); and
 -
Casting Seawall Block (in
Mainland China)
Contract no. HK/2009/01 - Wan Chai Development Phase II  Central –Wanchai
Bypass at HKCEC
 -
WA2 interim Engineer’s
Principal Office;
 -
Marine GI within the
Fairway and near Wan Chai West Pier;
 -
Fabrication of pipelines
at land portion of Cross Harbour Water Mains;
 -
Silt screen installation
for the existing cooling water intakes;
 -
Laying of electrical cable
ducting, cooling mains pipeworks at Area A1, A5 & B1 after the approval of
TTA;
 -
Silt screens at HKCEC
Extension will be installed;
 -
Silt screens for WSD pump
stations are scheduled for installation; and
 -
Fabrication of pile
staging
Contract no. HK/2009/02 - Wan Chai Development Phase II  Central  Wan
Chai Bypass at WanChai East
 -
Site Clearance;
 -
Hoarding Erection;
 -
Excavation;
 -
Removal Existing Footbridge
Staircase at Wan Shing Road;
 -
Pre-drilling Works at WSD
Salt Water Pumping Station;
 -
Commence Salt Water Intake
Culvert at Pet Garden;
 -
Road Modification Works;
 -
Construction of Temporary
Seawall;
 -
Dredging; and
 -
Tree Transplanting
1.1.1.
Lam Geotechnics Limited (LGL) has
been appointed to work as the
Environmental Team (ET) for Contractor No. HK/2009/05
Wan Chai Development Phase II and Central –Wan Chai Bypass  Sampling, Field
Measurement and Testing Work (Stage 1) to implement the Environmental Monitoring and Audit
(EM&A) programme as stipulated in the EM&A Manual of the
approved Environmental Impact Assessment (EIA) Report for Wan Chai Development
phase II and Central-Wan Chai Bypass (Register No.: AEIAR-125/2008) and in the
EM&A Manual of the approved EIA Report for Central-Wan Chai Bypass and
Island Eastern Corridor Link (Register No. AEIAR-014/2001).
1.1.2.
This report presents the environmental monitoring and
auditing work carried out in accordance to the Section
10.3 of EM&A Manual
and  /span>Environmental Monitoring and Audit
Requirements /span>
under Particular Specification Section 27.
1.1.3.
This report documents the
finding of EM&A works during the period 28th April to 27th May 2010. The
cut-off date of reporting is at 27th of each reporting month.
Section 1     Introduction
 details the scope and structure of the report.
Section 2     Project
Background  summarizes background and scope of the
project, site description, project organization and contact details of key
personnel during the reporting period.
Section 3     Status of Regulatory Compliance
 summarizes the status of valid Environmental Permits / Licenses during the
reporting period.
Section 4     Monitoring
Requirements
 summarizes all monitoring parameters, monitoring methodology and equipment,
monitoring locations, monitoring frequency, criteria and respective event and
action plan and monitoring programmes.
Section 5     Monitoring
Results  summarizes the monitoring results
obtained in the reporting period.
Section 6     Compliance
Audit  summarizes the auditing of
monitoring results, all exceedances environmental parameters.
Section 7     Cumulative Construction Impact due to the
Concurrent Projects  summarizes the relevant cumulative construction
impact due to the concurrent activities of the concurrent Projects.
Section 8     Site Inspection  
summarizes the findings of weekly site inspections undertaken within the
reporting period, with a
review of any relevant follow-up actions within the
reporting period.
Section 9     Complaints, Notification of summons and Prosecution
 summarizes the cumulative statistics on complaints,
notification of summons and prosecution
Section 10    Conclusion
2.1.1.
“Wan Chai Development phase II and Central-Wan Chai
Bypass and “Central-Wan Chai Bypass and Island Eastern Corridor Link 
(hereafter called “the Project  are Designed Project (DP) under the
Environmental Impact Assessment Ordinance (Cap. 499) (EIAO). The Environmental Impact Assessment (EIA) Reports
for Central-Wan Chai Bypass and Island Eastern Corridor Link (Register No.
AEIAR-041/2001) and Wan Chai Development phase II and Central-Wan Chai Bypass
(Register No.: AEIAR-125/2008) have been approved on 31 August 2001 and 11
December 2008 respectively.
2.1.2.
The key purpose of Wan Chai Development Phase II
(WDII) is to provide land at Wan Chai North and North Point for construction of
the Central-Wan Chai Bypass and Island Eastern Corridor Link (CWB). Land formed
under the project will be developed as a world-class waterfront promenade
joining that at the new Central waterfront for public enjoyment.
2.1.3.
There is a compelling and present need for the CWB to
provide relief to the very congested east-west Connaught Road Central/Harcourt
Road / Gloucester Road Corridor (the Corridor) which is currently operating
beyond its capacity. The CWB will provide relief to the existing congestion
along the Corridor and cater for the anticipated growth of traffic on Hong Kong
Island. Without the CWB and its access roads, there will not be sufficient
capacity to serve the heavy traffic demands at both strategic and local levels.
2.2.1.
The Project is located mainly in Wan Chai North,
Causeway Bay and North Point, and is demarcated by Gloucester Road and Victoria
Park Road to the south, Fenwick Pier Street to the west and Tong Shui Road
Interchange to the east, as shown in Figure 2.1.
2.2.2.
The study area encompasses existing developments along
the Wan Chai, Causeway Bay and North Point shorelines. Major land uses include
the Hong Kong Convention & Exhibition Centre (HKCEC) Extension, the Wan
Chai Ferry Pier, the ex-Wan Chai Public Cargo Working Area (ex-PCWA), the Royal
Hong Kong Yacht Club (RHKYC), the Police Officers' Club, the Causeway Bay
Typhoon Shelter (CBTS) and commercial and residential developments.
2.2.3.
The
scope of the Project comprises:
 -
Land formation for key
transport infrastructure and facilities, including the Trunk Road (i.e.
CWB) and the associated slip roads for connection to the Trunk Road and for through
traffic from Central to Wan Chai and Causeway Bay. The land formed for the above
transport infrastructure will provide opportunities for the development of an
attractive waterfront promenade for the enjoyment of the public
 -
Reprovisioning /
protection of the existing facilities and structures affected by the land
formation works mentioned above
 -
Extension, modification,
reprovisioning or protection of existing storm water drainage outfalls,
sewerage outfalls and watermains affected by the revised land use and land
formation works mentioned above
 -
Upgrading of hinterland
storm water drainage system and sewerage system, which would be rendered
insufficient by the land formation works mentioned above
 -
Provision of the ground
level roads, flyovers, footbridges, necessary transport facilities and the
associated utility services
 -
Construction of the new
waterfront promenade, landscape works and the associated utility services
 -
The
Trunk Road (i.e. CWB) within the study area and the associated slip roads for
connection to the Trunk Road.
2.2.4.
The project also contains various Schedule 2 DPs
that, under the EIAO, require Environmental Permits (EPs) to be granted by the
DEP before they may be either constructed or operated. Table 2.1 summarises the
five individual DPs under this Project. Figure 2.1
shows the locations of these Schedule 2 DPs.
Table 2.1   Schedule 2 Designated Projects under this
Project
Item |
Designated Project |
EIAO Reference |
Reason for inclusion |
DP1 |
Central-Wanchai Bypass (CWB) including its road tunnel and slip roads |
Schedule 2, Part I, A.1 and A.7 |
Trunk road and road tunnel more than 800 m in length |
DP2 |
Road P2 and other roads which are classified as primary/district
distributor roads |
Schedule 2, Part I, A.1 |
Primary / district distributor roads |
DP3 |
Reclamation works including associated dredging works |
Schedule 2, Part I, C.1 and C.12 |
Reclamation more than 5 ha in size and a dredging operation less than
100 m from a seawater intake point |
DP5 |
Wan Chai East Sewage Outfall |
Schedule 2, Part I, F.5 and F.6 |
Submarine sewage pipelines with a total diameter more than 1,200 mm
and include a submarine sewage outfall |
DP6 |
Dredging for the Cross-harbour Water Mains from Wan Chai to Tsim Sha
Tsui |
Schedule 2, Part I, C.12 |
A dredging operation less than 100 m from a seawater intake point |
2.3.1.
Due to the multi-contract nature of the Project,
there are a number of contracts sub-dividing the whole works area into
different work areas to be commenced. 
Contractors of individual contracts will be required by the EP holder to
apply Further Environmental Permits (FEP) such that the impact monitoring
stations are sub-divided accordingly to facilitate the implementation of
EM&A programme and to streamline the EM&A reporting for individual FEP
holders correspondingly.
2.3.2.
In the reporting month, Contract no. HY/2009/11 -
Central  Wanchai Bypass, North Point Reclamation under the Project has been
commenced on 17 March 2010. Two Contracts under the Project are anticipated to
be commenced in early of June 2010. 
The details of individual contracts are summarized in Table2.2.
Table 2.2  Details of Individual Contracts under the
Project
Contract No. |
Contract Title |
Associated DP(s) |
Construction Commencement Date |
HK/2009/01 |
Wan Chai Development Phase II  Central –Wanchai Bypass at Hong Kong
Convention and Exhibition Centre |
DP3, DP6 |
Early of June 2010 |
DP1, DP2 |
Pending |
||
HK/2009/02 |
Wan Chai Development Phase II  Central  Wan Chai Bypass at WanChai
East |
DP3, DP5 |
Early of June 2010 |
DP1 |
Pending |
||
HY/2009/11 |
Wan Chai Development Phase II and Central - Wan Chai Bypass - North
Point Reclamation |
DP3 |
17 March 2010 |
2.4.1.
Civil Engineering and
Development Department and Highways Department are the overall project
controllers for the Wan Chai Development Phase II and Central-Wan Chai Bypass
respectively.
For the construction phase of the Project, Project Engineer, Contractor(s),
Environmental Team and Independent Environmental Checker are appointed to
manage and control environmental issues.
2.4.2.
The proposed project organization and lines of
communication with respect to environmental protection works are shown in Figure 2.2. Key personnel and contact particulars are
summarized in Table 2.3:
Table 2.3  Contact Details of Key Personnel
Party |
Role |
Post |
Name |
Contact No. |
Contact Fax |
AECOM |
Engineer for WDII |
Chief Resident Engineer |
Mr. David Kwan |
2607 7801 |
2687 2322 |
Engineer for CWB |
Senior Resident Engineer |
Mr. Terry Siu |
3916 1818 |
3529 2829 |
|
China Harbour- CRBC Joint Venture |
Contractor under Contract no. HY/2009/11 |
Project Director |
Mr. Cho Yu Fun |
3157 1086 |
3157 1085 |
Project Manager |
Mr. Gregory Wong |
3157 1086 |
|||
Site Agent |
Mr. Daniel Cheung |
3157 1086 |
|||
Environmental Officer |
Mr. C. M. Wong |
3157 1086 |
|||
Chun Wo  Leader Joint Venture |
Contractor under Contract no. HK/2009/01 |
Site Agent |
Paul Yu |
9456 9819 |
2634 1626 |
Operation Manager |
Ho Wing Tai |
9306 1356 |
|||
Construction Manager |
David Wong |
9653 8635 |
|||
Construction Manager |
Wilson Lau |
5183 1270 |
|||
Construction Manager |
Alex Tsang |
9194 9383 |
|||
Environmental Officer
(Compliance Manager) |
Ho Wing Tai |
9306 1356 |
|||
Environmental Engineer |
Ken Yang |
9262 6791 |
|||
Chun Wo  CRGL Joint Venture |
Contractor under Contract no. HK/2009/02 |
Project Manager |
Mr. Chan Sing Cho |
3658 3002 |
2827 9996 |
Site Agent |
Mr. Anthony Wu |
3658 3004 |
|||
Environmental Officer (Compliance Manager) |
Mr. Barry Leung |
3658 3031 |
|||
Environmental Engineer |
Ms. Flora Ng |
3658-3064 |
|||
ENVIRON Hong Kong Limited |
Independent
Environmental Checker (IEC) |
Independent
Environmental Checker (IEC) |
Mr. David Yeung |
3743 0788 |
3548 6988 |
Lam Geotechnics Limited |
Environmental Team (ET) |
Environmental Team Leader (ETL) |
Mr. Raymond Dai |
2882 3939 |
2882 3331 |
2.4.3.
For Contract no. HY/2009/11, the principal work activities in this
reporting month included:
 -
Sediment dredging;
 -
Breakwater demolition;
 -
Special site hoarding
construction;
 -
Casting Caisson Seawall
(in Mainland China); and
 -
Casting Seawall Block (in
Mainland China).
2.4.4.
For Contract no. HK/2009/01, the site
preparation works
in this reporting month included:
 -
Erection of interim
Engineer’s Principal Office at Works areas WA2;
 -
Pre-drilling works and
fabrication of staging for trial pile, derrick barge is carrying out
transportation of materials to the designated pile position;
 -
Hoarding erection along
the southern and eastern side;
 -
Marine ground investigation;
 -
Installation of
geotechnical instrumentation is underway and inclinometers points of E1, E2,
E3, E4 and E8
 -
Fabrication of pipe pile
wall staging at the existing promenade piled deck;
 -
Inspection and structural
condition survey, field measurement for pumping stations P1, P3, P4 and P5;
 -
Fabrication of special
made flat top barge for dredging inside the HKCEC water channel;
 -
Silt screens installation
for HKCEC Phase 1, Government Buildings, China Resources, Great Eagle &
Harbour Centre, Telecom House, Shui On and HKAPA;
 -
Temporary silt curtain
installation at HKCEC Extension (Pumping Station P6);
 -
Fabrication of silt
screens for Sheung Wan & Kowloon South Pumping Station, and remaining HKCEC
Extension;
 -
Temporary works on the
existing promenade piled deck for installation of pipe pile wall P1;
 -
Existing RC. Parapet on
the north side of water channel near Expo Drive West Bridge was removed
partially; removal of rock amour on sloping seawall is in progress;
 -
Fabrication of mud barges
and crane barge for dredging within HKCEC water channel; and
 -
Wheel washing facility at
the north entrance to the water channel.
2.4.5.
For Contract no. HK/2009/02, the site
preparation works
in this reporting month included:
 -
Installation of Silt
Screen and Silt Curtain;
 -
Construction of Temporary
Seawall (Sheet Pile);
 -
Road Modification Works;
 -
Removal Existing Footing
at WSD Salt Water Pumping Station;
 -
Pre-drilling Works at WSD
Salt Water Pumping Station;
 -
Site Clearance; and
 -
Hoarding Erection
2.4.6.
In coming reporting month, the principal work
activities of individual contracts are anticipated as follows:
Contract
no. HY/2009/11- North Point Reclaimation
 -
Sediment dredging;
 -
Breakwater demolition;
 -
Casting Caisson Seawall
(in Mainland China); and
 -
Casting Seawall Block (in
Mainland China)
Contract
no. HK/2009/01 - Wan Chai Development Phase II  Central –Wanchai Bypass at
HKCEC
 -
WA2 interim Engineer’s
Principal Office;
 -
Marine GI within the
Fairway and near Wan Chai West Pier;
 -
Fabrication of pipelines
at land portion of Cross Harbour Water Mains;
 -
Silt screen installation
for the existing cooling water intakes;
 -
Laying of electrical cable
ducting, cooling mains pipeworks at Area A1, A5 & B1 after the approval of
TTA;
 -
Silt screens at HKCEC
Extension will be installed;
 -
Silt screens for WSD pump
stations are scheduled for installation; and
 -
Fabrication of pile
staging
Contract
no. HK/2009/02 - Wan Chai Development Phase II  Central  Wan Chai Bypass at
WanChai East
 -
Site Clearance;
 -
Hoarding Erection;
 -
Excavation;
 -
Removal Existing Footbridge
Staircase at Wan Shing Road;
 -
Pre-drilling Works at WSD
Salt Water Pumping Station;
 -
Commence Salt Water Intake
Culvert at Pet Garden;
 -
Road Modification Works;
 -
Construction of Temporary
Seawall;
 -
Dredging; and
 -
Tree Transplanting
3.1.1.
A summary of the current status on licences and/or
permits on environmental protection pertinent to the Project is shown in Table
3.1.
Permits and/or Licences |
Reference No. |
Issued Date |
Status |
Environmental
Permit |
EP-356/2009 |
30 Jul
2009 |
Valid |
Environmental
Permit |
EP-364/2009 |
17 Aug
2009 |
Valid |
Environmental
Permit |
EP-376/2009 |
13 Nov 2010 |
Valid |
Further Environmental Permit |
FEP-01/356/2009 |
18 Feb
2010 |
Valid |
Further Environmental Permit |
FEP-02/356/2009 |
24 Mar
2010 |
Valid |
Further Environmental Permit |
FEP-03/356/2009 |
24 Mar
2010 |
Valid |
Further
Environmental Permit |
24 Mar
2010 |
Valid |
|
Further
Environmental Permit |
21 Apr 2010 |
Valid |
3.1.2.
Due to the multi-contract nature of the Project, the
status of permits and/or licences under the individual contract(s) are
presented as below:
Contract no. HY/2009/11  Central  Wanchai
Bypass, North Point Reclamation
3.1.3.
Summary
of the current status on licences and/or permits on environmental protection
pertinent and
submission under FEP-01/356/2009 for
contract no. HY/2009/11
are shown in Table 3.2 and
Table 3.3.
3.1.4.
The new CNP no.
GW-RS0371-10 superseded the CNP no. GW-RS0119-10 for the dredging works during
any day not a general holiday between 1900-2300 and general holidays including
Sundays between 0700-2300. .
Table
3.2  Cumulative Summary of Valid
Licences and Permits under Contract no. HY/2009/11
Permits and/or Licences |
Reference No. |
Issued Date |
Valid Period/ Expiry Date |
Status |
Further Environmental Permit |
FEP-01/356/2009 |
18 Feb 2010 |
N/A |
Valid |
Notification of Works Under APCO |
314911 |
9 Mar 2010 |
N/A |
Valid |
Construction Noise Permit (CNP)
for non-piling equipment |
GW-RS0119-10 |
17 Feb 2010 |
22 Feb 2010 to 22 Aug 2010 |
Superseded |
GW-RS0371-10 |
7 May 2010 |
10
May 2010 to 10 Oct 2010 |
Valid |
|
GW-RS0437-10 |
20 May 2010 |
28
May 2010 to 27 Nov 2010 |
Valid (Replaced CNP no. GW-RS0119-10) |
|
Dumping Permit (Type 1  Open
Sea Disposal) |
EP/MD/10-067 |
10 Mar 2010 |
10 Mar 2010 to 9 Sep 2010 |
Valid |
Dumping Permit (Type 1  Open
Sea Disposal (Dedicate Sites) & Type 2  Confined Marine Disposal) |
EP/MD/10-082 |
8 Apr 2010 |
10
Apr 2010 to 9 May 2010 |
Expired |
EP/MD/11-003 |
6 May 2010 |
10
May 2010 to 9 Jun 2010 |
Valid |
Table 3.3  Summary
of submission status under FEP-01/356/2009 Condition
EP Condition |
Submission |
Date of Submission |
Condition 2.6 |
Management Organization of Main
Construction Companies |
18 Dec 2009 |
Condition 2.7 |
Submission of works schedule and location plan |
8 Feb 2010 |
Condition
2.8 |
Silt
Curtain Deployment Plan |
25 Feb 2010 |
Condition
2.9 |
Silt
Screen Deployment Plan |
25 Feb 2010 |
Condition
2.10 |
Coral
Translocation Plan |
20 Nov 2009 |
Condition
2.16 |
Noise
Management Plan |
1 Mar 2010 |
Condition
2.17 |
Landscape
Plan |
12
May 2010 |
Contract no. HK/2009/01 - Wan
Chai Development Phase II  Central –Wanchai Bypass at HKCEC
3.1.5.
Summary
of the current status on licences and/or permits on environmental protection
pertinent and
submission under FEP-02/356/2009 for
contract no.
HK/2009/01 are shown in Table 3.4 and
Table 3.5.
Table 3.4  Cumulative
Summary of Valid Licences and Permits under Contract no. HK/2009/01
Permits and/or Licences |
Reference No. |
Issued Date |
Valid Period/ Expiry
Date |
Status |
Further Environmental Permit |
FEP-02/356/2009 |
24 Mar 2010 |
N/A |
Valid |
Further Environmental Permit |
FEP-02/364/2009 |
21 Apr 2010 |
N/A |
Valid |
Notification of Works Under APCO |
313088 |
6 Jan 2010 |
N/A |
Valid |
Construction Noise Permit (CNP)
for non-piling equipment |
GW-RS0313-10 |
16 Apr 2010 |
16 Apr 2010 to 14 Sep 2010 |
Valid |
Construction Noise Permit (CNP)
for non-piling equipment |
GW-RS0328-10 |
22 Apr 2010 |
22 Apr 2010 to 15 Oct 2010 |
Valid |
Construction Noise Permit (CNP)
for non-piling equipment |
GW-RS0333-10 |
21 Apr 2010 |
21 Apr 2010 to 14 Sep 2010 |
Valid |
Construction Noise Permit (CNP)
for non-piling equipment |
GW-RS0336-10 |
21 Apr 2010 |
21 Apr 2010 to 14 Sep 2010 |
Valid |
Discharge Licence |
WT00006220-2010 |
18 Mar 2010 |
31 Mar 2015 |
Valid |
Registration as a Waste Producer |
WPN5213-134-C3585-01 |
21 Jan 2010 |
N/A |
Valid |
Dumping Permit (Type 1  Open
Sea Disposal) |
EP/MD/10-060 |
30 Apr 2010 |
4 May to 3 Nov 2010 |
Valid |
Dumping Permit (Type 1  Open Sea Disposal
(Dedicate Sites) & Type 2  Confined Marine Disposal) |
EP/MD/11-010 |
28 May 2010 |
1 Jun to 30 Jun 2010 |
Valid |
Table 3.5  Summary
of submission status under FEP-02/356/2009 Condition
EP Condition |
Submission |
Date of Submission |
Condition 2.6 |
Management Organization of Main
Construction Companies |
13 Apr 2010 |
Condition 2.7 |
Works Schedule and Location
Plan |
8 Apr 2010 |
Condition 2.8 |
Silt Curtain Deployment Plan |
19 Apr 2010 |
Condition 2.9 |
Silt Screen Deployment Plan |
19 Apr 2010 |
Condition 2.17 |
Noise Management Plan |
23 Apr 2010 |
Condition 2.18 |
Landscape Plan |
15 May 2010 |
Contract no. HK/2009/02 - Wan
Chai Development Phase II  Central  Wan Chai Bypass at WanChai East
3.1.6.
Summary
of the current status on licences and/or permits on environmental protection
pertinent and
submission under FEP-03/356/2009 for
contract no.
HK/2009/02 are shown in Table 3.6 and
Table 3.7.
Table 3.6  Cumulative
Summary of Valid Licences and Permits under Contract no. HK/2009/02
Permits and/or Licences |
Reference No. |
Issued Date |
Valid Period/ Expiry
Date |
Status |
Further Environmental Permit |
FEP-03/356/2009 |
24 Mar 2010 |
N/A |
Valid |
FEP-01/364/2009 |
24 Mar 2010 |
N/A |
Valid |
|
Notification of Works Under APCO |
313962 |
2 Feb 2010 |
N/A |
Valid |
Construction Noise Permit (CNP) for piling equipment |
PP-RS0016-10 |
14 Apr 2010 |
1 Jun 2010 to 31 Nov 2010 |
Valid |
Construction Noise Permit (CNP)
for non-piling equipment |
GW-RS0132-10 |
22 Feb 2010 |
01 Apr to 30 Sep 2010 |
Valid |
Construction Noise Permit (CNP)
for non-piling equipment |
GW-RS0325-10 |
16 Apr 2010 |
30 Apr to 31 Jul 2010 |
Valid |
Construction Noise Permit (CNP)
for non-piling equipment |
GW-RS0327-10 |
16 Apr 2010 |
30 Apr to 30 Sep 2010 |
Valid |
Discharge Licence |
WT00006249-2010 |
22 Mar 2010 |
31
Mar 2015 |
Valid |
WT00006436-2010 |
15 Apr 2010 |
30
Apr 2015 |
Valid |
|
WT00006673-2010 |
14 May 2010 |
31
Mar 2015 |
Valid |
|
Registration as a Waste Producer |
7010255 |
10 Feb 2010 |
N/A |
Valid |
Dumping Permit (Type 1  Open
Sea Disposal) |
EP/MD/10-069 |
6 May 2010 |
6 May to 5 Nov 2010 |
Valid |
Dumping Permit (Type 1  Open
Sea Disposal (Dedicate Sites) & Type 2  Confined Marine disposal) |
EP/MD/10-069 |
6 May 2010 |
6 May to 5 Jun 2010 |
Valid |
Table 3.7  Summary
of submission status under FEP-03/356/2009 Condition
EP Condition |
Submission |
Date of Submission |
Condition 2.6 |
Management Organization of Main
Construction Companies |
10 April 2010 |
Condition 2.7 |
Works Schedule and Location
Plans |
8 April 2010 |
25 May 2010 |
||
Condition 2.8 |
Silt Curtain Deployment Plan |
20 April 2010 |
25 May 2010 |
||
Condition 2.9 |
Silt Screen Deployment Plan |
21 April 2010 |
Condition 2.17 |
Noise Management Plan |
6 May 2010 |
Condition 2.18 |
Landscape Plan (Decorative
Screen Hoarding) |
11 May 2010 |
Figure 1b |
Updated General Layout |
22 May 2010 |
3.1.7.
Implementation status of the recommended mitigation
measures during this reporting period is presented in Appendix 3.1.
Noise Monitoring Stations
4.1.1.
The noise monitoring stations for the Project are
listed and shown in Table 4.1 and Figure 4.1.  /span>Appendix 4.1 shows the established Action/Limit
Levels for the monitoring works.
Table
4.1  Noise Monitoring Station
Station |
Description |
M1a |
Harbour
Road Sports Centre |
M2b |
Noon Gun Area |
M3a |
Tung Lo Wan Fire Station |
M4a |
Causeway
Bay Community Centre |
M5b |
City
Garden |
M6 |
HK Baptist Church Henrietta Secondary
School |
M7a |
Harbour
Building |
Noise Monitoring Parameters, Frequency
and Duration
4.1.2.
The construction noise level shall
be measured in terms of the A-weighted equivalent continuous sound
pressure level (Leq). Leq (30 minutes) shall be used as
the monitoring parameter for the time period between 0700
and 1900 hours on normal weekdays. For all other time periods, Leq (5
minutes) shall be employed for comparison with the Noise Control
Ordinance (NCO) criteria. Supplementary information for
data auditing, statistical results such as L10 and L90 shall also be obtained
for reference.
4.1.3.
Noise monitoring shall be carried out at all
the designated monitoring stations. The monitoring frequency shall depend on
the scale of the construction activities. The following is an initial guide on
the regular monitoring frequency for each station on a weekly basis when noise
generating activities are underway:
 -
one set of measurements between 0700 and 1900
hours on normal weekdays.
4.1.4.
If construction works are extended to include
works during the hours of 1900  0700 as well as public holidays and Sundays,
additional weekly impact monitoring shall be carried out during respective
restricted hours periods. Applicable permits under NCO shall be obtained by the
Contractor.
Monitoring Equipment
4.1.5.
As referred to in the Technical Memorandum
(TM) issued under the NCO, sound level meters in compliance with the
International Electrotechnical Commission Publications 651: 1979 (Type 1) and
804: 1985 (Type 1) specifications shall be used for carrying out the noise
monitoring. Immediately prior to and following each noise measurement the
accuracy of the sound level meter shall be checked using an acoustic calibrator
generating a known sound pressure level at a known frequency. Measurements may
be accepted as valid only if the calibration level from before and after the
noise measurement agree to within 1.0 dB.
4.1.6.
Noise measurements shall not be made in fog,
rain, wind with a steady speed exceeding 5 m/s or wind with gusts exceeding 10
m/s. The wind speed shall be checked with a portable wind speed meter capable
of measuring the wind speed in m/s.
4.1.7.
The sound level meter shall be checked using
an acoustic calibrator generating a known sound pressure level at a known
frequency before deployment to the site and during each site visit.
Measurements may be accepted as valid only if the calibration level from before
and after the noise measurement agree to within 1.0 dB.
Air Quality Monitoring Stations
4.2.1.
The air monitoring stations for the Project
are listed and shown in Table 4.2 and Figure 4.1. Appendix 4.1 shows the established
Action/Limit Levels for the monitoring works.
Table 4.2  Air Monitoring Station
Station ID |
Monitoring Location |
Description |
CMA1b |
Oil Street Community Liaison Centre |
North
Point |
CMA2a |
Causeway Bay Community Centre |
Causeway
Bay |
CMA3a |
Future CWB site office at Wanchai
Waterfront Promenade |
Causeway
Bay |
CMA4a |
Society for the Prevention of
Cruelty to Animals |
Wan Chai |
CMA5a |
Children Playgrounds opposite to
Pedestrian Plaza |
Wan Chai |
CMA6a |
Future AECOM site office at Work
Area |
Wan Chai |
MA1b |
Harbour
Building |
Central |
Air Monitoring Parameters, Frequency and
Duration
4.2.2.
One-hour and 24-hour TSP levels should be
measured to indicate the impacts of construction dust on air quality. The
24-hour TSP levels shall be measured by following the standard high volume
sampling method as set out in the Title 40 of the Code of Federal Regulations,
Chapter 1 (Part 50), Appendix B.
4.2.3.
All relevant data including temperature,
pressure, weather conditions, elapsed-time meter reading for the start and stop
of the sampler, identification and weight of the filter paper, and any other
local atmospheric factors affecting or affected by site conditions, etc., shall
be recorded down in detail.
4.2.4.
For regular impact monitoring, the sampling
frequency of at least once in every six-days, shall be strictly observed at all
the monitoring stations for 24-hour TSP monitoring. For 1-hour TSP monitoring,
the sampling frequency of at least three times in every six-days should be
undertaken when the highest dust impact occurs.
Sampling Procedure and Monitoring
Equipment
4.2.5.
High volume samplers (HVSs) in compliance
with the following specifications shall be used for carrying out the 1-hour and
24-hour TSP monitoring:
 -
0.6 - 1.7 m3 per minute adjustable flow
range;
 -
equipped with a timing / control device with
+/- 5 minutes accuracy for 24 hours operation;
 -
installed with elapsed-time meter with +/- 2
minutes accuracy for 24 hours operation;
 -
capable of providing a minimum exposed area
of 406 cm2;
 -
flow control accuracy: +/- 2.5% deviation
over 24-hour sampling period;
 -
equipped with a shelter to protect the filter
and sampler;
 -
incorporated with an electronic mass flow
rate controller or other equivalent devices;
 -
equipped with a flow recorder for continuous
monitoring;
 -
provided with a peaked roof inlet;
 -
incorporated with a manometer;
 -
able to hold and seal the filter paper to the
sampler housing at horizontal position;
 -
easily changeable filter; and
 -
capable of operating continuously for a
24-hour period.
4.2.6.
Initial calibration of dust monitoring
equipment shall be conducted upon installation and thereafter at bi-monthly
intervals. The transfer standard shall be traceable to the internationally
recognized primary standard and be calibrated annually. The concern parties
such as IEC shall properly document the calibration data for future reference.
All the data should be converted into standard temperature and pressure
condition.
Laboratory Measurement / Analysis
4.2.7.
A clean laboratory with constant temperature
and humidity control, and equipped with necessary measuring and conditioning
instruments to handle the dust samples collected, shall be available for sample
analysis, and equipment calibration and maintenance. The laboratory should be
HOKLAS accredited.
4.2.8.
Filter paper of size 8" x 10" shall
be labeled before sampling. It shall be a clean filter paper with no pinholes,
and shall be conditioned in a humidity-controlled chamber for over 24-hours and
be pre-weighed before use for the sampling.
4.2.9.
After sampling, the filter paper loaded with
dust shall be kept in a clean and tightly sealed plastic bag. The filter paper
shall then be returned to the laboratory for reconditioning in the humidity
controlled chamber followed by accurate weighing by an electronic balance with
readout down to 0.1 mg. The balance shall be regularly calibrated against a
traceable standard.
4.2.10. All
the collected samples shall be kept in a good condition for 6 months before
disposal.
4.3.1.
The EIA Report has identified that the key
water quality impact would be associated with the dredging works during the
construction phase. Marine water
quality monitoring for dissolved oxygen (DO), suspended solid (SS) and
turbidity is therefore recommended to be carried out at selected WSD flushing
water intakes. The impact monitoring
should be carried out during the proposed dredging works to ensure the
compliance with the water quality standards.
Water Quality Monitoring Stations
4.3.2.
It is proposed to monitor the water quality
at 9 WSD salt water intakes and 12 cooling water intakes along the seafront of
the Victoria Harbour. The proposed water quality monitoring stations of the
Project are shown in Table 4.3 and Figure 4.1. Appendix 4.1 shows the established
Action/Limit Levels for the monitoring works.
Table
4.3   Marine Water Quality Stations for
Water Quality Monitoring
Station Ref. |
Location |
Easting |
Northing |
WSD Salt
Water Intake |
|||
WSD7 |
Kowloon South |
834150.0 |
818300.3 |
WSD9 |
Tai Wan |
837921.0 |
818330.0 |
WSD10 |
Cha Kwo Ling |
841900.9 |
817700.1 |
WSD15 |
Sai Wan Ho |
841110.4 |
816450.1 |
WSD17 |
Quarry Bay |
839790.3 |
817032.2 |
WSD19 |
Sheung Wan |
833415.0 |
816771.0 |
WSD20 |
Kennedy Town |
830750.6 |
816030.3 |
WSD21 |
Wan Chai |
836220.8 |
815940.1 |
RW1 |
Wan Chai (Reprovision) |
836188.8 |
815911.1 |
Cooling
Water Intake |
|||
C1 |
HKCEC Extension |
835885.6 |
816223.0 |
C2 |
Telecom House |
835647.9 |
815864.4 |
C3 |
HKCEC Phase I |
835836.2 |
815910.0 |
C4 |
Wan Chai Tower and Great Eagle
Centre |
835932.8 |
815888.2 |
C5 |
Sun Hung Kai Centre |
836250.1 |
815932.2 |
C6 |
World Trade Centre |
837009.6 |
815999.3 |
C7 |
Windsor House |
837193.7 |
816150.0 |
C8 |
City Garden |
837970.6 |
816957.3 |
C9 |
Provident Garden |
838355.0 |
817116.6 |
RC1 |
Proposed
HKAPA Extension |
835487.7 |
815987.7 |
RC5 |
Sun Hung
Kai Centre (Reprovision) |
836291.4 |
816029.7 |
RC7 |
Windsor House (Temporary Dilution) |
837245.2 |
816156.6 |
Water Quality Parameters
4.3.3.
Monitoring of dissolved oxygen (DO),
turbidity and suspended solids (SS) shall be carried out at WSD flushing water
intakes and cooling water intakes. DO and Turbidity are measured in-situ while
SS is determined in laboratory. 
4.3.4.
In association with the water quality
parameters, other relevant data shall also be measured, such as monitoring
location/position, time, sampling depth, water temperature, pH, salinity,
dissolved oxygen (DO) saturation, weather conditions, sea conditions, tidal
stage, and any special phenomena and work underway at the construction site
etc.
Sampling Procedures and Monitoring
Equipment
4.3.5.
The interval between two sets of monitoring
should not be less than 36 hours except where there are exceedances of Action
and/or Limit Levels, in which case the monitoring frequency will be
increased. Table 4.4 shows the
proposed monitoring frequency and water quality parameters. Duplicate in-situ measurements and water
sampling should be carried out in each sampling event. For selection of tides for in-situ
measurement and water sampling, tidal range of individual flood and ebb tides
should be not less than 0.5m.
Table
4.4  Marine Water Quality Monitoring
Frequency and Parameters
Activities |
Monitoring Frequency1 |
Parameters2 |
During the 4-week baseline
monitoring period |
Three days per week, at mid-flood
and mid-ebb tides |
Turbidity, Suspended Solids (SS),
Dissolved Oxygen (DO), pH, Temperature, Salinity |
During marine
construction works |
Three days per week, at mid-flood
and mid-ebb tides |
Turbidity, Suspended Solids (SS),
Dissolved Oxygen (DO), pH, Temperature, Salinity |
After
completion of marine construction works |
Three days per week, at mid-flood
and mid-ebb tides |
Turbidity, Suspended Solids (SS),
Dissolved Oxygen (DO), pH, Temperature, Salinity |
Notes:
1. For
selection of tides for in-situ measurement and water sampling, tidal range of
individual flood and ebb tides should be not less than 0.5m.
2. Turbidity
should be measured in situ whereas SS should be determined by laboratory.
Dissolved Oxygen and Temperature
Measuring Equipment
4.3.6.
The instrument should be a portable,
weatherproof dissolved oxygen measuring instrument complete with cable, sensor,
comprehensive operation manuals, and use a DC power source. It should be capable of measuring:
 -
a dissolved oxygen level in the range of 0-20
mg/l and 0-200% saturation
 -
a temperature of 0-45 degree Celsius
4.3.7.
It should have a membrane electrode with
automatic temperature compensation complete with a cable. Sufficient stocks of spare electrodes and
cables should be available for replacement where necessary. (e.g. YSI model 59
meter, YSI 5739 probe, YSI 5795A submersible stirrer with reel and cable or an
approved similar instrument).
4.3.8.
Should salinity compensation not be build-in
in the DO equipment, in-situ salinity shall be measured to calibrate the DO
equipment prior to each DO measurement.
Turbidity Measurement Instrument
4.3.9.
The instrument should be a portable,
weatherproof turbidity-measuring instrument complete with comprehensive
operation manual. The equipment should
use a DC power source. It should have a
photoelectric sensor capable of measuring turbidity between 0‑1000 NTU
and be complete with a cable (e.g. Hach model 2100P or an approved similar instrument).
Sampler
4.3.10. A
water sampler comprises a transparent PVC cylinder, with a capacity of not less
than 2 litres, and can be effectively sealed with latex cups at both ends. The sampler should have a positive latching
system to keep it open and prevent premature closure until released by a
messenger when the sampler is at the selected water depth (e.g. Kahlsico Water
Sampler or an approved similar instrument).
Sample Container and Storage
4.3.11. Water
samples for suspended solids measurement should be collected in high-density
polythene bottles, packed in ice (cooled to 4°C without being frozen), and
delivered to ALS Technichem (HK) Pty Ltd. as soon as possible after collection
for analysis.
Water Depth Detector
4.3.12. A
portable, battery-operated echo sounder shall be used for the determination of
water depth at each designated monitoring station. This unit can either be handheld or affixed to the bottom of the
workboat, if the same vessel is to be used throughout the monitoring
programme. 
Salinity
4.3.13. A
portable salinometer capable of measuring salinity in the range of 0-40 ppt
shall be provided for measuring salinity of the water at each of monitoring
location.
Monitoring Position Equipment
4.3.14. A
hand-held or boat-fixed type digital Global Positioning System (GPS) with way
point bearing indication or other equivalent instrument of similar accuracy
shall be provided and used during monitoring to ensure the monitoring vessel is
at the correct location before taking measurements.
Calibration of In-situ Instruments
4.3.15. All
in-situ monitoring instrument shall be checked, calibrated and certified by a
laboratory accredited under HOKLAS or equivalent before use, and subsequently
re-calibrated at 3 monthly intervals throughout all stages of the water quality
monitoring. Responses of sensors and electrodes should be checked with
certified standard solutions before each use. 
Wet bulb calibration for a DO meter shall be carried out before
measurement at each monitoring location.
4.3.16. For
the on site calibration of field equipment by the ET, the BS 127:1993,
"Guide to Field and on-site test methods for the analysis of waters"
should be observed.
4.3.17. Sufficient
stocks of spare parts should be maintained for replacements when
necessary. Backup monitoring equipment
shall also be made available so that monitoring can proceed uninterrupted even
when some equipment is under maintenance, calibration, etc.
4.3.18. Current
calibration certificates of equipments are presented in Appendix
4.2.
Laboratory Measurement / Analysis
4.3.19. Analysis
of suspended solids has been carried out in a HOKLAS accredited laboratory, ALS
Technichem (HK) Pty Ltd. Water samples
of about 1L shall be collected at the monitoring stations for carrying out the
laboratory SS determination. The SS
determination work shall start within 24 hours after collection of the water
samples. The SS determination shall
follow APHA 19ed or equivalent methods subject to the approval of IEC and EPD.
5.0.1.
The environmental monitoring will be
implemented based on the division of works areas of each designed project
managed under different contracts with separate FEP applied by individual
contractors. Overall layout showing
work areas of various contracts, latest status of work commencement and
monitoring stations is shown in Figure
2.1 and Figure 4.1. The monitoring results
are presented in according to the Individual Contract(s).
5.0.2.
In the reporting month, the current contract
has Contract no. HY/2009/11 Central - Wan Chai Bypass - North Point Reclamation
under Permanent and temporary reclamation works including associated dredging
works in Wan Chai Development Phase II (WDII) area (referred to as DP3 in the
EIA Report).
5.0.3.
The environment monitoring schedules for
reporting month and coming month are presented in Appendix
5.1.
Contract
no. HY/2009/11  Central  Wanchai Bypass, North Point Reclamation
5.1.1.
The proposed division of noise monitoring
stations for Contract no. HY/2009/11 are summarized in Table 5.1 below:
Table 5.1   Noise Monitoring Stations for Contract no.  /span>HY/2009/11
Station |
Description |
M4a |
Causeway Bay Community Centre |
M5b |
City Garden |
5.1.2.
Four day time and evening period noise
monitoring was conducted at the City Garden and Causeway Bay Community Centre in
the reporting month.
5.1.3.
Noise monitoring results measured in this
reporting period are reviewed and summarized. 
Details of noise monitoring results and graphical presentation can be
referred in Appendix 5.2. 
5.1.4.
One action level exceedance
was recorded due to the noise complaint, ICC case: 1-233384048 on 4 May 2010.
It was complained on the construction noise nuisance from the dredging works
from 1900 to 0800. The details of the complaint can be referred to Section 9
and Appendix 9.1.
5.1.5.
One limit level exceedance
was recorded at M4a- Caseway Bay Community Centre on 4 May 2010. Contractor for
Contract no. HY/2009/11 was granted CNP no GW-RS0119-10 for the
dredging works. According to the RSS’s record, there was no day
time and evening time works conducted for dredging in the period between 29 April to
5 May 2010. It is considered as invalid exceedance.
Contract
no. HK/2009/01 - Wan Chai Development Phase II  Central –Wanchai Bypass at
HKCEC and Contract no. HK/2009/02 - Wan Chai Development Phase II  Central  
Wan Chai Bypass at WanChai East
5.1.6.
The commencement of marine construction works
for Contract nos. HK/2009/01 and HK/2009/02 are anticipated in early of June
2010. The noise monitoring will be commenced concurrently with the commencement
of construction works for these two contracts. The proposed division of noise
monitoring stations are summarized in Table 5.2 below.
Table 5.2
  Noise Monitoring Station for Contract nos. HK/2009/01 and HK/2009/02
Station |
Description |
M1a |
Harbour Road Sports Centre |
Contract
no. HY/2009/11  Central  Wanchai Bypass, North Point Reclamation
5.2.1.
The major construction activities of Contract
no. HY/2009/11 was dredging works in the reporting month. No major dust impact
is anticipated to be caused by the dredging works. Therefore, no air monitoring
was conducted in the reporting month.
5.2.2.
Air monitoring will be commenced from the
filling work for Contract no. HY/2009/11. The proposed division of air
monitoring stations are summarized in Table 5.3 below.
Table 5.3
  Air
Monitoring Stations for Contract no. HY/2009/11
Station |
Description |
CMA1b |
Oil Street Community Liaison Centre |
CMA2a |
Causeway Bay Community Centre |
Contract
no. HK/2009/01 - Wan Chai Development Phase II  Central –Wanchai Bypass at
HKCEC
5.1.7.
Air monitoring will be commenced from the
filling work for Contract no. HK/2009/01. The proposed division of air
monitoring stations are summarized in Table 5.4 below.
Table 5.4
  Air
Monitoring Stations
for Contract
no. HK/2009/01
Station |
Description |
CMA5a |
Children Playgrounds opposite to Pedestrian Plaza |
CMA6a |
Future AECOM site office at Work Area 1 |
Contract
no. HK/2009/02 - Wan Chai Development Phase II  Central  Wan Chai Bypass at
WanChai East
5.1.8.
Air monitoring will be commenced from the
filling work for Contract no. HK/2009/02. The proposed division of air
monitoring stations are summarized in Table 5.5 below.
Table 5.5
  Air
Monitoring Station for Contract no. HK/2009/02
Station |
Description |
CMA4a |
Society for the Prevention of Cruelty to Animals |
Contract
no. HY/2009/11  Central  Wanchai Bypass, North Point Reclamation
5.3.1.
The proposed division of water monitoring
stations for Contract no. HY/2009/11 are summarized in Table 5.6 below:
Table 5.6
  Water Monitoring Stations for Contract no.  /span>HY/2009/11
Station Ref. |
Location |
Easting |
Northing |
WSD Salt Water Intake |
|||
WSD9 |
Tai Wan |
837921.0 |
818330.0 |
WSD10 |
Cha Kwo Ling |
841900.9 |
817700.1 |
WSD15 |
Sai Wan Ho |
841110.4 |
816450.1 |
WSD17 |
Quarry Bay |
839790.3 |
817032.2 |
Cooling Water Intake |
|||
C8 |
City Garden |
837970.6 |
816957.3 |
C9 |
Provident Garden |
838355.0 |
817116.6 |
5.3.2.
13 water monitoring were conducted at the
proposed water monitoring stations in reporting month.
5.3.3.
Due to the amber rainstorm warning and
thunderstorm on 19 May 2010 during mid-ebb, we concern about the safety during work
over water under adverse weather and consider the water quality being
substantially affected by urban runoff did not represent the normal impact
condition. At such, water quality
monitoring for this tide was cancelled.
5.3.4.
Water monitoring results measured in this
reporting period are reviewed and summarized. 
Details of water quality monitoring results and graphical presentation
can be referred in Appendix 5.3.
5.3.5.
For the suspended solid, total
one action level exceedances and four limit level exceedances were recorded in
the reporting month. The details of exceedances are as follows:
 -
One action level
exceedance was recorded at C9 on 14 May 2010 during mid-flood;
 -
Two limit level
exceedances were recorded at WSD17 on 17 May 2010 during mid-flood and 26 May
2010 during mid-ebb;
 -
Two limit level
exceedances were recorded at C9 on 28 April 2010 during mid-flood and on 26 May
2010 during mid-ebb.
5.3.6.
For the turbidity, total four
limit level exceedances were recorded in the reporting month. The details of exceedances are as follows:
 -
Two limit level
exceedances were recorded at C8 on 28 April 2010 during mid-flood and 10 May
2010 during mid-ebb; and
 -
Two limit level exceedances
were recorded at C9 on 28 April and 14 May 2010 during mid-flood.
Contract
no. HK/2009/01 - Wan Chai Development Phase II  Central –Wanchai Bypass at
HKCEC
5.3.7.
Water monitoring for Contract no.
HK/2009/01 is anticipated to be commenced on early of June. Installations of
silt screen and silt curtain are untaken in the reporting month. The proposed
division of water monitoring stations are summarized in Table 5.7 below.
Table 5.7
  Water Monitoring Stations for Contract no.HK/2009/01
Station Ref. |
Location |
Easting |
Northing |
WSD Salt Water Intake |
|||
WSD7 |
Kowloon South |
834150.0 |
818300.3 |
WSD19 |
Sheung Wan |
833415.0 |
816771.0 |
WSD20 |
Kennedy Town |
830750.6 |
816030.3 |
Cooling Water Intake |
|||
C1 |
HKCEC Extension |
835885.6 |
816223.0 |
C2 |
Telecom House |
835647.9 |
815864.4 |
C3 |
HKCEC Phase I |
835836.2 |
815910.0 |
C4 |
Wan Chai Tower and Great
Eagle Centre |
835932.8 |
815888.2 |
Remarks:
The water monitoring stations for
the dredging works under Contract No. HK/2009/01 should also include WSD9,
WSD17, WSD 21 and C5 if water quality monitoring at these locations have not
been carried out by others. Similarly, the water monitoring stations for the
dredging works under Contract No. HK/2009/02 should also include WSD7, WSD9,
WSD17, WSD 19, C1, C2, C3 and C4 if water quality monitoring at these locations
have not been carried out by others.
Contract
no. HK/2009/02 - Wan Chai Development Wan Chai Development Phase II  Central  
Wan Chai Bypass at WanChai East
5.3.8.
Water monitoring for Contract no. HK/2009/02
is anticipated to be commenced on early of June Installations of silt screen
and silt curtain are untaken in the reporting month. The proposed division of water
monitoring stations are summarized in Table 5.8 below.
Table 5.8
  Water Monitoring Stations for Contract no. HK/2009/02
Station Ref. |
Location |
Easting |
Northing |
WSD Salt Water Intake |
|||
WSD21 |
Wan Chai |
836220.8 |
815940.1 |
Cooling Water Intake |
|||
C5 |
Sun Hung Kai Centre |
836250.1 |
815932.2 |
Remarks:
The water monitoring stations for
the dredging works under Contract No. HK/2009/01 should also include WSD9,
WSD17, WSD 21 and C5 if water quality monitoring at these locations have not
been carried out by others. Similarly, the water monitoring stations for the
dredging works under Contract No. HK/2009/02 should also include WSD7, WSD9,
WSD17, WSD 19, C1, C2, C3 and C4 if water quality monitoring at these locations
have not been carried out by others.
Contract
no. HY/2009/11  Central  Wanchai Bypass, North Point Reclamation
5.4.1.
Non-inert C&D waste and marine sediment
were disposed of in the reporting month. Details of the waste flow table are
summarized in Table 5.9.
Table 5.9  Details
of Waste Disposal for Contract no. HY/2009/11
Waste
Type |
Quantity this month, m3 |
Cumulative Quantity-to-Date, m3 |
Disposal / Dumping Grounds |
Inert C&D materials disposed |
NIL |
NIL |
N/A |
Inert C&D materials recycled |
NIL |
NIL |
N/A |
Non-inert C&D materials disposed |
4.72 |
4.72 |
SENT Landfill |
Non-inert C&D materials recycled |
NIL |
NIL |
N/A |
Chemical waste disposed |
N/A |
N/A |
N/A |
Marine Sediment (Type 1  Open Sea Disposal) |
4,000 |
36,000 |
South of Cheung Chau |
Marine Sediment (Type 1  Open Sea Disposal
(Dedicate Sites) & Type 2  Confined Marine Disposal) |
2,500 |
46,000 |
East of Sha Chau |
There were
marine sediments Type 1  Open Sea Disposal and Type 1  Open Sea Disposal
(Dedicate Sites) & Type 2  Confined Marine Disposal marine sediment
disposed in the reporting month. The maximum dredging rate in North Point
Shoreline Zone is 1,500m3 per day in the reporting month, which is complied
with the criteria listed in Table 5.10 of EIA Report Register No. AEIAR-125/2008.
Contract no. HK/2009/01 - Wan Chai Development Phase II  Central –Wanchai
Bypass at HKCEC
5.4.2.
Non-inert C&D waste was disposed of for
the site preparation works in this reporting month. Details of the waste flow
table are summarized in Table 5.10.
Table 5.10 Details
of Waste Disposal for Contract no. HK/2009/01
Waste
Type |
Quantity this month, m3 |
Cumulative Quantity-to-Date, m3 |
Disposal / Dumping Grounds |
Inert C&D materials disposed |
NIL |
NIL |
N/A |
Inert C&D materials recycled |
NIL |
NIL |
N/A |
Non-inert C&D materials disposed |
12 |
24 |
SENT Landfill |
Non-inert C&D materials recycled |
NIL |
NIL |
N/A |
Chemical waste disposed |
NIL |
NIL |
N/A |
Marine Sediment (Type 1  Open Sea Disposal) |
NIL |
NIL |
N/A |
Marine Sediment (Type 1  Open Sea Disposal
(Dedicate Sites) & Type 2  Confined Marine Disposal) |
NIL |
NIL |
N/A |
Contract no. HK/2009/02 - Wan Chai Development Phase II  Central  Wan
Chai Bypass at WanChai East
5.4.3.
Non-inert C&D waste was disposed of for
the site preparation works in this reporting month. Details of the waste flow
table are summarized in Table 5.11.
Table 5.11 Details
of Waste Disposal for Contract no. HK/2009/02
Waste
Type |
Quantity this month, m3 |
Cumulative Quantity-to-Date, m3 |
Disposal / Dumping Grounds |
Inert C&D materials disposed |
NIL |
NIL |
N/A |
Inert C&D materials recycled |
NIL |
NIL |
N/A |
Non-inert C&D materials disposed |
22 |
22 |
SENT Landfill |
Non-inert C&D materials recycled |
NIL |
NIL |
N/A |
Chemical waste disposed |
NIL |
NIL |
N/A |
Marine Sediment (Type 1  Open Sea Disposal) |
NIL |
NIL |
N/A |
Marine Sediment (Type 1  Open Sea Disposal
(Dedicate Sites) & Type 2  Confined Marine Disposal) |
NIL |
NIL |
N/A |
6.0.1.
The Event Action Plan for construction noise,
air quality and water quality are presented in Appendix 6.1.
6.1.1.
One action level exceedance
was recorded due to the noise complaint, ICC case: 1-233384048 on 4 May 2010.
It was complained on the construction noise emission from the dredging works
from 1900 to 0800. According to the records of RSS, no dredging activities have
been conducted from 29 April to 5 May 2010. 
It considered as invalid complaint. The details of the complaint can be
referred to Section 9 and Appendix 9.1.
5.1.9.
One limit level exceedance
was recorded at M4a Community Centre on 4 May 2010. Contractor for Contract no.
HY/2009/11 was granted CNP no GW-RS0119-10 for the dredging works. According to the RSS’s record, there was no daytime
and evening time works conducted for dredging in
the period between 29 April and 5 May 2010. It is considered as invalid
exceedance.
6.2.1.
No air monitoring was conducted in this
reporting period.
6.3.1.
For the suspended solid, total
one action level exceedances and four limit level exceedances were recorded in
the reporting month. The details of exceedances are as follows:
 -
One action level
exceedance was recorded at C9 on 14 May 2010 during mid-flood;
 -
Two limit level
exceedances were recorded at WSD17 on 17 May 2010 during mid-flood and 26 May
2010 during mid-ebb;
 -
Two limit level
exceedances were recorded at C9 on 28 April 2010 during mid-flood and on 26 May
2010 during mid-ebb.
6.3.2.
For the turbidity, total four
limit level exceedances were recorded in the reporting month. The details of exceedances are as follows:
 -
Two limit level
exceedances were recorded at C8 on 28 April 2010 during mid-flood and 10 May
2010 during mid-ebb;
 -
Two limit level
exceedances were recorded at C9 on 28 April and 14 May 2010 during mid-flood.
6.3.3.
The action and limit level exceedances of
turbidity and suspended solid were recorded at C8 and C9. Major exceedances
were occurred during the mid-flood tide in the water quality monitoring.
Investigation was found that the numerous unknown outfalls from the nearby
coastal area enclosed by the silt screen at C8 and C9. It causes the potential for accumulation and
trapping of pollutants behind the silt screens and may lead
to potential water quality deterioration at the seawater intake points. Contractor
was reminded to avoid the pollutant and refuse entrapment problems.
Besides, regular
maintenance of the silt screens and refuse collection shall be performed at the
monitoring stations at regular intervals on a daily basis.
6.3.4.
The limit level exceedance was recorded at
WSD17 on 26 May 2010. No muddy boom was
observed during the water monitoring. Reviewed the data of the nearest
monitoring station to the marine work area in the same tide, no exceedance was
recorded. As such, it is concluded as natural variation and non-project related
exceedance. Summary for notification of exceedances can be referred to Appendix 6.2.
6.4.1.
There was no non-compliance from the site
audits in the reporting period. The observations and recommendations made in
each individual site audit session were presented in Section 8.
6.4.2.
No project-related non-compliance from
monitoring was recorded in the reporting month.
6.5.1.
There was no particular action taken since no project-related
non-compliance was recorded from the site audits and environmental monitoring
in the reporting period.
7.0.1.
According to Condition 3.4 of the
EP-356/2009, this section addresses the relevant cumulative construction impact
due to the concurrent activities of the current projects including the Central Reclamation,
Central-Wan Chai Baypass and Island Eastern Corridor Link projects.
7.0.2.
From the Monthly EM&A report (April 2010)
of Central Reclamation Project, the key works in May 2010 are as follows:
 -
Type A filling in FRAW and
FRAE above +2.5mPD;
 -
General filling works
above +2.5 mPD in IRAE;
 -
Surcharging in FRAW and
FRAE;
 -
Construction of cantilever
slab at caisson;
 -
Pile cap construction at
Culvert F;
 -
Sheet piling, excavation,
structural works and backfilling for Culvert F;
 -
Construction of storm and
foul drainage and gullies in hinterlands for Road P2;
 -
Road D7, Road D8 and Road
D9 and adjacent to the GPO;
 -
Roadworks along Lung Wui
Road, Tim Wa Avenue (Road D8) and Road P2;
 -
Road P2 Underpass ramp
structures;
 -
Backfilling to Culvert K
extension;
 -
Pre-casting for retaining
wall (offsite);
 -
Installation of cooling
water mains for Tamar Development Project;
 -
Installation of cooling
mains discharge pipes in FRAE;
 -
Diaphragm wall and
barrettes for CWB Works; and
 -
Excavation to formation
level at CWB works.
7.0.3.
According to the construction programme of Central-Wan
Chai Baypass and Island Eastern Corridor Link projects, the major construction activity
under Wan Chai Development Phase II was the dredging work at North Point Reclamation
Stage 1 in the reporting month. The major environmental impact was water
quality impact at North Point.  /span>No
construction activities were undertaken in the Central-Wan Chai Baypass and
Island Eastern Corridor Link projects.
7.0.4.
The major environmental impacts generated from
the Central Reclamation Projects were located along the coastline of Central
and Admiralty while only dredging work at North Point Reclamation Stage 1 was
in operation in this reporting month. Beside,
water quality mitigation measures were properly in place for the dredging works
under Contract no. HY/2009/11 in this reporting month. No project –related
exceedance were recorded. Thus, it is evaluated that the cumulative
construction impact from the concurrent projects including Wan Chai Development
Phase II and Central Reclamation was insignificant.
8.0.1.
Four site inspections for Contract no.
HY/2009/11 were carried out during this reporting period. The results of these inspections and
outcomes are summarized in Table 8.1.
Table
8.1  Summary
of Environmental Inspections for Contract
no. HY/2009/11
Item |
Date |
Observations |
Action taken by Contractor |
Outcome |
100504_01 |
4-May-10 |
Contractor is reminded to clean the debris behind
the silt screen at Sai Wan Ho. |
Daily clearance and
inspection of silt screen. |
Complete as
observed on 18-May-10 |
100512_01 |
12-May-10 |
Floating refuse at WSD15 need to be cleaned up. |
Daily clearance and inspection of silt screen. |
Complete as
observed on 18-May-10 |
100518_01 |
18-May-10 |
Floating refuse was observed at C9. |
Daily clearance and inspection of silt screen. |
Complete as
observed on 25-May-10 |
100518_02 |
18-May-10 |
Floating foam of silt screen was observed lower than sea level at
WSD17. It is reminded to well maintain the condition of silt screen
immediately. |
Follow-up action is needed for coming site audit |
Outstanding as observed on 25 May 2010 |
100518_03 |
18-May-10 |
It is reminded to fence-off the silt curtain
properly around the dredging
and filling works area. |
Keep maintaining the silt curtain in well
condition. |
Complete as observed on 25-May-10 |
100518_04 |
18-May-10 |
It is reminded to maintain and repair the silt
screen at C8 regularly. |
Follow-up action is needed for coming site audit |
Outstanding as observed on 25 May 2010 |
100525_01 |
25-May-10 |
A gap was found at the right side (view from boat)
of the silt screen at Quarry Bay. |
Follow-up action is needed for coming site audit |
Outstanding as observed on 25 May 2010 |
9.0.1.
One noise complaint was recorded from ICC on
4 May 2010 regarding the construction noise emission from dredging works at
North Point district between 1900 and 0800. Contract no. HY/2009/11 has the
valid CNP for the dredging works between 1900 and 2300. No dredging works have
been conducted after 2300. Contractor has implemented mitigation measures to
reduce the working hour not later than 2230. 
According to the records of RSS, no dredging activities have been
conducted in the period between 29 April to 5 May 2010. The details of cumulative complaint log and
summary of complaints are presented in Appendix 9.1.
9.0.2.
Cumulative statistic on complaints and
successful prosecutions are summarized in Table 9.1 and Table 9.2 respectively.
Table 9.1  Cumulative
Statistics on Complaints
Reporting Period |
No. of Complaints |
May 2010 |
1 |
Project-to-Date |
3 |
Table 9.2  Cumulative Statistics on Successful Prosecutions
Environmental Parameters |
Cumulative No. Brought Forward |
No. of Successful Prosecutions this month (Offence Date) |
Cumulative No. Project-to-Date |
Air |
- |
0 |
0 |
Noise |
- |
0 |
0 |
Water |
- |
0 |
0 |
Waste |
- |
0 |
0 |
Total |
- |
0 |
0 |
9.0.3.
An
incident regarding the suspected breach of Marine Dumping Permit for Contract
no. HY/2009/11 by EPD letter dated 20 April 2010, RSS has conducted a site
investigation with Contractor on 22 April 2010. Contractor for Contract no.
HY/2009/11 has reported the details of the incident and their improvement
measures to EPD on 23 April 2010. According to the EPD letter dated 20 May
2010, they have invited Contractor to assist the investigation for their
explanation or clarification on the above incident. Any updated information
will be reported in the next reporting report.
10.0.1. The
EM&A programme was carried out in accordance with the EM&A Manual
requirements, minor alterations to the programme proposed were made in response
to changing circumstances.
10.0.2. The
scheduled construction activities and the recommended mitigation measures for
the coming month are listed in Table 10.1.
Table
10.1 Construction
Activities and Recommended Mitigation Measures in Coming Reporting Month
Contract
No. |
Key Construction Works |
Recommended
Mitigation Measures |
HY/2009/11 |
 -
Sediment dredging;  -
Breakwater demolition;  -
Casting Caisson Seawall (in Mainland China); and  -
Casting Seawall Block (in Mainland China). |
 -
To avoid concurrent noisy operation  -
Daily visual inspection of silt screen and silt curtain to ensure its
operation properly  -
Daily clearance of floating debris behind the silt screen |
10.0.3. In
the coming month, the Contracts HK/2009/01 and HK/2009/02 are anticipated to be
commenced on site are summarized in Table 10.2. The construction
programmes of individual contracts are provided in Appendix 10.1.
Table 10.2 Summary
of Key Construction Activities of Individual Contract(s) to be commenced in Coming Reporting Month
Contract
No. |
Key Construction Activities |
Recommended Mitigation Measures |
HK/2009/01 |
 -
WA2 interim Engineer’s Principal Office;  -
Marine GI within the Fairway and near Wan Chai West
Pier;  -
Fabrication of pipelines at land portion of Cross
Harbour Water Mains;  -
Silt screen installation for the existing cooling
water intakes;  -
Laying of electrical cable ducting, cooling mains
pipeworks at Area A1, A5 & B1 after the approval of TTA;  -
Silt screens at HKCEC Extension will be installed;  -
Silt screens for WSD pump stations are scheduled
for installation; and  -
Fabrication of pile staging |
 -
To conform the installation and setting as in the silt screen
deployment plan  -
Frequency spray water on the dry dusty road and on the surface of
concrete breaking  -
To cover the dusty material or stockpile by impervious sheet  -
To space out noisy equipment and position
as far as possible from sensitive receiver.  -
To well maintain the mechanical equipments
/ machineries to avoid abnormal noise nuisance.  -
Machines and plant that may be in
intermittent use should be shut down between work periods or should be
throttled down to a minimum |
HK/2009/02 |
 -
Site clearance  -
Hoarding Erection;  -
Excavation;  -
Removal Existing Footbridge Staircase at Wan Shing Road;  -
Pre-drilling Works at WSD Salt Water Pumping Station;  -
Commence Salt Water Intake Culvert at Pet Garden;  -
Road Modification Works;  -
Construction of Temporary Seawall;  -
Dredging; and  -
Tree Transplanting |
 -
To cover the dusty material or stockpile by impervious sheet;  -
Frequency spray water on the dry dusty road and on the surface of
concrete breaking  -
To well maintain the mechanical equipments / machineries to avoid
abnormal noise nuisance and dark smoke emission  -
To conform the installation and setting as in the silt screen and silt curtain deployment plan |